Q: FAQ: RF Testing in production
The prototypes and the first batch should go through qualification testing.For later batches, samples can be submitted to qualification tests and remaining devices to production test.The level of testing must be seen in connection with cost and consequence of failure or poor performance as well asstability in manufacturing processes.Qualification test:
The tests may be determined by the instruments that is possessedMore information about sensitivity testing can be found in design note 002:http://www.ti.com/litv/swra097Information about antenna measurements with network analyzer:http://www.ti.com/litv/swra096