ADS54J60EVM: ADS54J60EVM

Part Number: ADS54J60EVM

Tool/software:

Hi 

I am programming the ADS54J60EVM via USB. Although TI supplies setup program, I have to make SPI programming for my design.

In the SPI programming I have trouble in power down the ADC. According to the datasheet. 0011h -80h should be sent for master page selection. And then "0055h-40h sent for mask enable. For global power down "0026h-80h" is sent but there was no change in the current of DC power supply. Is it correct the procedure and the data stream for power down the ADC?

Thank you in advance for the help.

K. W. Yeom