ISO7762-Q1: Is there timing requirement to work ISO776x-Q1 after power up VCC?

Part Number: ISO7762-Q1

Hi team,

Our customer asked us about a question to ISO776x-Q1.

Is there timing requirement to wait ISO776x-Q1 between power up VCC and operation? Does customer need to wait some time after power up VCC?

Regards,

Nishimura

  • Hi Nishimura,

    Like every other device ISO776x will also take some finite time for it to power-up and operate normally. The startup time for ISO776x is typically expected to be about 100µs while it can go upto 180µs for under worst-case conditions. It is best to operate the device only after 180µs after VCCx > 2.25V. Thanks.

    Regards,

    Koteshwar Rao