I hope it was possible to gain more insight on the highlighted circuit in the bq25713 EVM. Can TI provide the vulnerabilities a system would have if this circuit was not included in a design?
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi Kevin,
That part of the design is to prevent inrush current and can be broken down into 2 parts.
1.
This is the soft start part.
2.
This part enables the soft start based on the CHRG_OK signal. Otherwise, the FETs would never turn on.
I would recommend running a SPICE simulation first with the first part, then slowly incorporate the second part. This part of the design is not necessary for the charger itself to work.
Thanks and I hope this helps,
Peng