Other Parts Discussed in Thread: LAUNCHXL-CC2640R2, USB2ANY, BQ25792, BQSTUDIO, EV2400
Hi Team,
Can you help with the inquiry below?
A customer is building a BLE solar power battery backup soil monitoring system to a central hub.
The system consists of:
PV has a 6-7V with max of 330mA
(1S) Samsung 50E 27500 5000mAh and 9.7A output battery
the load is a LAUNCHXL-CC2640R2
The customer followed EVM and BQ manual and moved pins to where It is needed and opened the GUI then tried to select the options they need however, Some options is not selectable (disabled check box), such as EN MPPT and EN_backup_mode. Also, the D13 (STAT LED) will not light even after being jumped, and the LED does operate when a Diode tester is used.
Shunt locations:
JP1 1-2
JP2 1-2
JP5 – THE INSTRUCTIONS MADE IT SOUND TO BE INSTALLED SO THEY DID. Please confirm if correct.
JP7 1-2
JP8 1-2 – THE INSTRUCTIONS MADE IT SOUND TO BE INSTALLED SO THEY DID.
JP9 1-2 -- THE INSTRUCTIONS MADE IT SOUND TO BE INSTALLED THIS ORIENTATION SO THEY DID.
JP12
JP14 – ILIM_HIZ_SET IS CONFUSING AS WELL SO THEY SET AT THE 1.5A. MAY BE WRONG. PLEASE CONFIRM.
JP17
JP18
JP22
JP30
JP32
JP33
Please let me know if you need more information.
Regards,
Marvin