Hi Team,
Could you please help to advise whether TI has done phase margin testing for the TLV760 LDO?
Phase margin testing method reference document "Ti_snoa507" as attached.
Best regards,
Terry
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi Team,
Could you please help to advise whether TI has done phase margin testing for the TLV760 LDO?
Phase margin testing method reference document "Ti_snoa507" as attached.
Best regards,
Terry
Hey Terry,
In lab measurements for stability are not necessarily performed during the validation process. The designers typically simulate the stability measurements and we test stability through transient load steps.
We recommend doing NISM to test for the same thing.
Best,
Juliette