Part Number: BQ78350-R1

Hi team

We use bq78350 without CEDV algorithm (CEDV Gauging Configuration = 0x0002).

Please let I know the relation range of DOD at EDV2.

Is there any process that refers to DOD at EDV2 other than the device estimates the initial capacity of a battery pack?

Best regards, 

Pls forgive my poor English.

Masa

1 Reply

  • Hi Masa,

    DOD at EDV2 is used for initial capacity estimation but it is also used when calculating the updated FCC at the end of a qualified cycle. It is also updated along with FCC. 

    Best regards,

    Matt

     TI provides design resources and design advice (including technical, schematic, code and/or system review) “as is” and with all faults.  All information in this or related correspondence is provided subject to TI’s Important Notice (http://www.ti.com/corp/docs/legal/important-notice.shtml).

This thread has been locked.

If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.