My customer has a design in which rails will be powered down in an uncontrolled order.
Any risk if VLDOIN is powered down before VDD?
Datasheet recommends powered down VDD before VLDOIN.
Thanks.
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
My customer has a design in which rails will be powered down in an uncontrolled order.
Any risk if VLDOIN is powered down before VDD?
Datasheet recommends powered down VDD before VLDOIN.
Thanks.
Thanks, Qian.
What about the other rails? Any risks turning off any others in a particular uncontrolled sequence?
Hi Gregory,
No risk on TPS51206 side. You may need to check the sequence requirement from DIMM side.
Thanks
Qian