Hi team,
Is "all of DRV5053 lead surface" coated by SN?
"All of DRV5053 lead surface" means lead top, bottom, left and right side coating.
Regards,
Ochi
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi team,
Is "all of DRV5053 lead surface" coated by SN?
"All of DRV5053 lead surface" means lead top, bottom, left and right side coating.
Regards,
Ochi
Ochi-san,
We are verifying with the assembly and test for you. We expect to be able to respond Monday.
Thanks,
Scott Bryson
Ochi-san,
Can you specify whether you are interested in the SOT-23 or the TO-92 package?
Thanks,
Scott
Hi Scott,
Sorry for late reply.
I am interested in TO-92 package so far.
Regards,
Ochi
Ochi-san,
Thank you for clarifying. I was able to get confirmation of the process for the DBZ package, it may take until after 2/17 to receive an answer from the assembly site due to Chinese New Year celebrations.
The DBZ package has plating on all surfaces, however there is a dam bar which is cut after the plating process, so in this area there will not be Sn at the cut area.
Scott
Ochi-san,
The assembly site did respond that they are looking into the LPG package. We anticipate a response before the end of week. We thank you for your continued patience.
Regards,
Scott
Ochi-san,
The LPG lead frame is processed in the same fashion as the DBZ package. The lead is plated on all surfaces, except for at the dam bar cut location.
Thanks,
Scott