Are there any power-down sequencing requirements for the 948?
Section 9.2 talks about the power-up sequence, but I don't see anything about powering it down.
Thanks
-Tyler
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi Team,
Are there any power-down sequencing requirements for the 948?
Section 9.2 talks about the power-up sequence, but I don't see anything about powering it down.
Thanks
-Tyler
Hi Tyler,
No requirements/special considerations when powering down the 948.
Regards,
Logan