Hi,
I noticed the grid current measurements of phase 1 and 2 are swapped before entering the DSP, in the TIDM-1000.
This can be verified by checking the waveforms at the TP_IL1, TP_IL2 testpoints.
Cheers,
Devinda
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Devinda,
The TP are marked incorrectly, I'll file a bug but it is not something that will be fixed soon, as we have no hardware revision planned for this.
Thanks for bringing this to our attention.
Regards
Manish Bhardwaj