Hi
Page 18 of the datasheet contains a four-phase SCH.
Is the external clock shown required to configure four-phase?
I want to implement 8kw, is it possible with one ucc28070? Or do I have to make a four-phase with two ucc28070?
Thanks
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi
Page 18 of the datasheet contains a four-phase SCH.
Is the external clock shown required to configure four-phase?
I want to implement 8kw, is it possible with one ucc28070? Or do I have to make a four-phase with two ucc28070?
Thanks
Hi David,
Thank you for the query on UCC28070.
It would be better to go with a four phase design with 2 UCC28070 controllers for such high power using external synchronization as you have shown above. We do not have a reference design showing this external synchronization feature between multiple modules.
Regards,
Harish