Hi Mike,
I am running the PSFB topology with Diode full bridge on the secondary side of the converter with UCC28951 controller. As I increase load above 250W, the converter generates loud noise. From the waveform, I found that the effective duty cycle varies a lot with a fixed resistive load. Duty cycle changes form 1usec to 2usec. This phenomenon is observed above 50% of full load (250W). Does it have to do with the compensation network? If yes, then how to optimize the compensator components?
Vin=400V, Vout=24V, Pout=500W, Fsw=200kHz
Here are the waveforms:
CH1: VDS of QA
CH2: VGS of QA
CH3: VDS of QC
CH4: VGS of QC
CH6: Voltage across the transformer [Effective Duty cycle]
Thank you.