Hi,
May I ask the MP time of LM5143-Q1?
PGND and AGND ,are them isolation?
Thanks!
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hello Neal Zhu.
Are you asking RTM (Release to Market) time?
And yes PGND and AGND are isolated. Power Ground (PGND) directly connected to all high-power components and an analog ground (AGND) plane for sensitive analog components. The analog ground plane for AGND and power ground planes for PGND1 and PGND2 must be connected at a single point directly under the IC – at the die attach pad (DAP).
Best Regards,
Ankit Gupta
Application Engineer.
Hi Neal,
Let me get the date from program manager of this part.
Best Regards,
Ankit Gupta
Hello Neal,
Release to Market (RTM) date is expected to be last week of October.
Best Regards,
Ankit Gupta
Application Engineer