Hi,
I am searching a step by step procedure that lead me on the integration of the circuit with the BQ40Z80 and the battery cells.
I found only SLUA868–June 2018 bq40z80 Manufacture, Production, and Calibration, but this doc doesn't explain the sequence of the activities:
Connection with the cells, design and update of the firmware and finally upload of the golden image on the new pack.
Is there a sequence?
Should I connect the cell first and after I can work on the firmware or the sequence is the opposite?
Are there other tasks that I should I do for a safety integration of the battery pack (and that can help me to avoid the jeopardizing of the electronics and cells)?
Thanks,
Fabrizio.