Hi Team,
my customer has a question about the TPS65982 reference circuit that shown on the latest Intel Apline Ridge reference design as attached, at page 6 of the reference design, the RPD_G1/G2 are connected to the C_CC1/2 together, while the previous version of the reference design has the RPD_G1/G2 connected to GND.
So, customer wants to know what are the purposes of this circuit changed? and should they need to follow up this changed? Or they can still keep the RPD_G1/G2 connected to GND for their system appliation that only supports 5V/3A single type C port?
Please advise. Thanks.