Are there power sequencing requirements on the PCA9306-Q1? Can the customer power up VREF1 first, then after a period of time (seconds or minutes) can they then apply power to VREF2. If this is OK, can it be done vice versa, VREF2 comes on first, then VREF1 comes on at a later time.
I do not think that this would be an issue, but I just wanted to verify that there are no power sequencing issues with this part.
Thanks for your help with this!
Richard Elmquist