Hello,
Our customer use the SN65DSI84, have question about initialization sequence.
It is mentioned as follows at recommended initialization sequence on the datasheet.
1.Power on. DSI lanes LP11.
2.Assert the EN pin.
The sequence of the customer is as follows,
1. Power on and assert the EN pin 1ms later from power is stable.
2.DSI lanes LP11
3. De-assert the EN pin. (Reset time)
4.Assert the EN pin
Is it OK?
Best Regards,
Naoki Aoyama