This thread has been locked.

If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.

TUSB4041I: Power up timing requirements

Part Number: TUSB4041I

Hi,

I would like to ask the Power up timing requirements of the datasheet.

I think that (1) is mentioned about the time from power-on to the GSTz, however the td1 is specified the time of relation during VDD and VDD33.

What is relation between td1 and note(1)?

About note(2), what does "power-on relationship" mean?

Best Regards,

Kuramochi

  • HI TQ,

    The ramp order of 3.3V and 1.1V (power-on relationship) only matters if the application is using a passive reset circuit. In that case, td1 applies. If there is an active reset to the hub, then only td2 applies to GRSTz timing.

    Regards,
    JMMN