This thread has been locked.

If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.

SN74LVC1G125: _OE and Vcc off timing for Ioff function

Other Parts Discussed in Thread: SN74LVC1G125, SN74LVC1G34

rt Number: SN74LVC1G125

Hi,

My customer is using SN74LVC1G125 in below circuit.
Customer want to avoid pump of VccB when VccB is not supplied.
Customer will input High level to _OE before power down VccB from MCU.
Could you answer below questions for doing complete Ioff, please?

Q1: For avoid pump of VccB by source current from VccA, How long time should customer wait between High input of _OE and power down of VccB?

Q2: Should we watch the slope of power down VccB voltage after _OE is high? Does this device have limitation of voltage slope for Ioff function?


Best regards,
Shimizu