Dear production team,
we ordered 1000 units of the MSP432E411YTZADR at the end of November 2022 via our distributor digi key. The delivery was scheduled for February 12, 2023. Now there is no delivery date. According to digi key, they only know about 26 weeks typical delivery time.
This situation is not satisfactory for us, because our production depends on this controller. If the delivery cannot be guaranteed, we would have to start a software and hardware redesign in the coming months.
Is there any way to increase the priority for production of this device and get an estimated delivery date?