Tool/software:
Hey SafeTI Team,
I have a customer working with the Safety compiler qualification kit (SAFETI_CQKIT) for a project and we were hoping you could help to clarify some of our questions from the TQP (Tool Qualification Plan) template in that kit. Please see a summary of our questions below!
We are trying to fill out the "Tool Qualification Plan for TI C/C++ Compiler",
but we have some questions. (Validation-based qualification is expected to be performed)
What does “component” in “3.5.1 Use Case Definitions” refer to? Is there an example of how to fill this out?

For example, assume we have a c28x project, and there are 3 projects for each CPU.
Should I fill in the project name?
Section 3.5.4 says that we need to submit the coverage files to TI.
Who should we send this to?
And how long does it take to get the comparison result?

We would like to know how this qualification process works in order to prepare early.
https://e2e.ti.com/cfs-file/__key/communityserver-discussions-components-files/908/TQP.docm
-Matt