Is the TMS320VC5510 power supply sequencing critical? The SPRAA43A application note seems to imply that it is but thus far I have been unable to find a reference as to what the proper sequence should be.
Thanks,
Bowen
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Is the TMS320VC5510 power supply sequencing critical? The SPRAA43A application note seems to imply that it is but thus far I have been unable to find a reference as to what the proper sequence should be.
Thanks,
Bowen
As recommended by TI the core should be powered before IO, however what is undocumented is that if after boot the IO is not needed then it can be shut down to save power, we do this in power critical applications and have not come across any negative effects.
Ed