Hi Diego:
Customer confused with the below information:
PCM3008 does not need a specific phase relationship between LRCK and system clock, but does require the synchronization of LRCK and system clock.
If the relationship between system clock and LRCK changes more than ±4 BCK during one sample period
Could you give us some steps of testing synchronization? Or some diagram?
Many thanks!
Regards!
Luck Wu