Hi all,
We meet a strange situation: Customer test their dock with HP Sepctre Laptop and it will ask 15V PDO in CC communication. When our FW version is v1.12.0, we can communicate with HP NB successfully when the NB power is in all power condition. But when we change FW version to v1.12.6, we can't success to make up the cc connection in power if NB battery is higher than 90%, and the link process will be retry and can't process alt mode communication. Here're the experiments we test on
1. We test another two FW. the same setting in v1.12.2 can pass the test, but v1.12.5 is failed.
2. If we remove 15V PDO on the setting in v1.12.6 FW, the communication is ok.
Please help to advise what should we have to do to clear the issue. Thanks for your kindly help.
The fig. below are the condition in different power status (91% in left, 89% in right).TPS65982_1p12p06b.pjt
Best regards,
Gary Teng
Hi Aramis,
1. Please see the attached file about log of transmission.raw.zip
2. I have no idea why there's different result about different battery capability in HP's TBT NB. Our dock is type-c power source with fix PDO voltage and don't have battery in our side.
3. Dell is pushing our customer to solve the issue ASAP. Do you have any comment for us to clear it? Measuring HW signal or...?
Thanks for your kindly help.
Gary
Hi Gary,
Since we closed this thread, could you PLEASE select This resolved my issue
Thank you so much for your question and choosing TI parts for your design :-)