In our application VDD3 is on first followed by a lowering of VDD3 and then VDD is sequenced on first with VDD3 following approximately 1 second later.
We experience no operational problems, but my question is:
With GRSTZ connected only to a capacitor, if VDD3 and VDD are not sequenced correctly (VDD must be stable minimum of 10 μs before the VDD33) is this just a violation of guaranteed operation or is the device subject to potential damage?
I am asking because we have experienced several failures of TUSB4041 in between manufacturing of a PCBA and the same PCBA's integration into a system in our factory.
Attached is image of sequencing:trace 1 is VDD3, trace 2 is VDD