from the schematic above POE_NET15 is supposed to be disconnectoed to Vss(pin 7 of U3"TPS23753APW")
but from ther gerber data there is a connection between FB2 and VSS.
which one is right?
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
from the schematic above POE_NET15 is supposed to be disconnectoed to Vss(pin 7 of U3"TPS23753APW")
but from ther gerber data there is a connection between FB2 and VSS.
which one is right?
Hello jiyoung chang,
Above image is not showing up clearly, could you please re-post the image?
Thanks and regards,
CHETHAN KUMAR Y.B.
sorry, due to the security issues, it's hard to capture the image and upload it.
but this circuit is given by TI also the gerber data is given by TI Design files of "MMWAVEPOEEVM"
please check the schmatic and gerber data of Design files and let me know which one is correct...
okay. i see
i thought the cross symbol(X) on the POE_NET15 means "disconnection".
so you mean POE_NET15 must be connected to "VSS", is it right?
then, what does the cross symbol(X) mean?
The X is to suppress ERC
https://www.altium.com/documentation/altium-designer/sch-obj-noercno-erc-ad?version=19.1