My customer wants to know TMDS171's powerup sequence in datasheet.
Which is the power up sequence faster the Vcc/Vdd and Vdd/Vcc?
I cannot understand power up sequence follow figure in datasheet.
Best regards.
Hayashi
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi teams.
My customer wants to know TMDS171's powerup sequence in datasheet.
Which is the power up sequence faster the Vcc/Vdd and Vdd/Vcc?
I cannot understand power up sequence follow figure in datasheet.
Best regards.
Hayashi
Hi Hayashi,
The previous datasheet requested Vdd to be applied before Vcc, this new figure tries to show the order between Vcc and Vdd doesn't matter as OE=L at least 100us(td2) after both Vcc and Vdd are stable.
Regards
Hi,
about the power-up timing,
VCC (or VDD) must be stable before VDD (or VCC) within 200us (or VCC and VDD stable within 200us),
all right?
If not verified, does this condition to lead to latch-up problems?
Thank you.
BR