TPS659039-Q1: Is there any requirement of time sequence about SMPS and LDO after power on?

Part Number: TPS659039-Q1

Dears:

Could you kindly help to check the below schematic?

Is there any requirement of time sequence about SMPS and LDO after power on? 

  

Thanks a lot!

Best regards

Luck Wu

  • Hi,

    The parts of the schematic shown here look fine. The LDO and SMPS rails automatically turn on once the device is enabled. They have a programmed timing sequence already configured and do not need any other requirements.

    There are several orderable part numbers of the TPS659039-Q1 that have the different voltage and sequencing configurations.

    Please let me know if this answers your questions.


    Thanks,
    Nastasha
  • Dear Nastasha:
    Thanks for your help.
    The PN is O9039A387IZWSRQ1 and what is the part's voltage and sequencing configurations?
    How can I find the materials about these configurations?
    Thanks a lot!

    Best regards
    Luck Wu
  • Luck,

    The configurations can be found in the user guide: http://www.ti.com/lit/pdf/swcu175

    Figure 1 will show the default voltages for the 0x87 OTP that you are using. Sections 4 - 6 will show you the rest of the default settings, including the power sequencing.

    Please let me know if you need anything else.

    Thanks,

    Nastasha