This thread has been locked.

If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.

[FAQ] AM625/AM623 Custom board hardware design – Processor power-sequencing requirements for power-up and power-down

  1. Hi TI Experts,

    I have the below queries regarding SOC(Processor) power-sequencing requirements for power-up and power-down

    1.Is there a recommended power sequence to be followed for power-up?
    2.Is there a power supply ramp requirement to be followed for power-up?
    3.Is there a timing requirement to be followed between supply ramps (supply ramp delay time after the previous supply ramps)
    4.Are there any other sequencing requirements that are required to be considered?
    5.Is there a recommended power sequence to be followed for power-down?
    6.Is there a power supply ramp requirement to be followed for power-down?
    7.In the power-down sequence, the MCU_PORz goes low after the power supplies start to ramp down. Is this expected?
    8.Could you comment on the effect of not following the power-up and power-down on SOC (Processor) performance?
    9.Are these recommendations applicable for all the Sitara family of devices

    Let me know your thoughts.

  • Hi Board designers,
    Refer below inputs for the SOC(Processor) power-sequencing requirements for power-up and power-down


    1.Is there a recommended power sequence to be followed for power-up?
    Follow the Power-Up Sequencing Figure and Power-Up Sequencing – Supply / Signal Assignments table of the processor specific data sheet


    2.Is there a power supply ramp requirement to be followed for power-up?
    Refer to Power Supply Slew Rate Requirement section and Power Supply Slew and Slew Rate figure of the processor specific data sheet


    3.Is there a timing requirement to be followed between supply ramps ( supply ramp delay after the previous supply ramps)
    There is not specific timing requirement to be followed between 2 supply ramps. It is recommended to ensure the previous supply ramps and is stable before start of the next supply ramp


    4.Are there any other sequencing requirements that are required to be considered?
    Refer to the notes below the Power-Up Sequencing – Supply / Signal Assignments table of the processor specific data sheet


    5.Is there a recommended power sequence to be followed for power-down?
    Follow the Power-Down Sequencing figure and Power-Down Sequencing – Supply / Signal Assignments table of the processor specific data sheet


    6.Is there a power supply ramp down requirement to be followed for power-down?
    We do not have any specific power supply ramp down requirements to be followed. This is use case dependent.
    The power supply is recommended to be turned on after the supply voltages ramp down below 0.3V.

    The important consideration is following the sequence and Power Supply Slew Rate Requirement.
    The supply rails connect to different internal IP blocks that are powered as the supply ramps.
    Although there is no specified time, it would be recommended to have time that allows the power supply to become stable and also allow time for the internal circuit to setup and complete the configuration.


    7.In the power-down sequence, the MCU_PORz goes low after the power supplies start to ramp down. Is this expected?
    It is drawn that way to represent how things actually work. Power supply supervisors will need to trigger at a voltage that is few percent lower than
    the minimum valid level before it generates a reset. So the reset will occur delayed relative the beginning of the supply falling.
    We expect customers to assert MCU_PORz as soon as possible to ensure the IO cells do not do something unexpected as the IO supply decays.
    So they should pick a threshold for the voltage supervisor that is close to the minimum valid level without being so close that is generates
    false resets. We expect customers to generate reset based on the state of all supplies, where the first one that ramps down will assert reset
    as soon as possible to ensure the device is in a know state as all of the supplies continue to ramp down.


    8.Could you comment on the effect of not following the power-up and power-down on SOC (Processor) performance?
    The data sheet provides the recommend & tested power sequencing diagram that should be followed. We do not characterize the power-up and power-down
    sequence violation as part of the validation. Violating the power down sequence could likely result in issues related to device reliability.
    TI does not collect reliability data on unsupported conditions (i.e. power sequences other than recommended), therefore TI cannot say whether
    the SoC will operate reliably or that it may fail at any time.


    9.Are these recommendations applicable for all the Sitara family of devices
    This is applicable for AM64x, AM62x, AM62Ax, AM62Px

    Regards,

    Sreenivasa

  • Hi Board designers,

    Additional inputs on the supply slew rate:

    The power supply slew rate is only defined for power-up. This slew rate limit is required to prevent the ESD circuits implemented on the power pins from accidently triggering. This is not a concern for power-down.

    Regards,

    Sreenivasa