Hi,
Could you tell me the latest RTM schedule of TLV9061?
I have checked the following thread.
Best Regards,
Kuramochi
This thread has been locked.
If you have a related question, please click the "Ask a related question" button in the top right corner. The newly created question will be automatically linked to this question.
Hi,
Could you tell me the latest RTM schedule of TLV9061?
I have checked the following thread.
Best Regards,
Kuramochi
Hello,
Samples of the TLV9061 in the DPW package can be ordered now. The DPW package is expected to fully RTM in 4Q.
The DCK and DBV package variants are expected to RTM in 3Q.
Thank you,
Tim Claycomb
Hello,
I made a mistake in my previous post regarding the RTM date of the DPW package.
The DPW package is expected to fully RTM in 4Q.
The TLV9061 in the DPW package will fully RTM in approximately 1 week.
The DCK and DBV package variants are expected to RTM in 3Q.
Thank you,
Tim Claycomb
Tim,
Thanks for the confirmation as the DBV is not yet in the back of the datasheet but mentioned at the front page.